Asphalt Road in Birendranagar Municipality

We are proud to announce the successful completion of the Integrated Infrastructure Development Works at Birendranagar Municipality, Surkhet, a transformative urban infrastructure project aimed at enhancing connectivity, resilience, and quality of life for the growing population of this vital provincial capital.

Project Overview:

  • Project Name: Integrated Infrastructure Development Works

  • Location: Birendranagar Municipality, Surkhet

  • Total Road Length: 16.035 km

  • Project Duration: 28 Months

  • Scope Includes: Asphalt Concrete Road, RCC Drainage, Retaining Walls

Scope of Work:

The project focused on comprehensive urban road and infrastructure upgrades, including:

  • Construction of 16.035 km of road, designed for long-term durability and improved urban mobility.

  • Asphalt Concrete Surfacing for smoother, high-performance roadways suitable for mixed traffic flow.

  • RCC Drain Construction to ensure effective stormwater management and minimize flooding during monsoon seasons.

  • Retaining Walls for slope protection and structural stability, especially in vulnerable sections.

Key Achievements:

  • Successfully delivered a multi-component urban development project in 28 months.

  • Improved transportation infrastructure and drainage systems, directly benefiting residents and local businesses.

  • Strengthened urban resilience through well-engineered retaining structures and durable pavements.

This project marks a major step toward sustainable urban development in Birendranagar, aligning with the vision of modernizing infrastructure across Karnali Province. We extend our gratitude to the local community, technical teams, and stakeholders who contributed to this milestone.

Mangalgadi Road, Birendranagar

We are pleased to announce the successful completion of the Mangalgadi – Ganeshchowk Road Project in Birendranagar, Surkhet, a key urban road infrastructure upgrade enhancing mobility and urban development in the region. The project was executed over 23 months, transforming a critical transportation corridor into a modern, durable, and high-capacity roadway.

Project Overview:

  • Project Name: Mangalgadi – Ganeshchowk Road Construction

  • Location: Birendranagar Municipality, Surkhet

  • Completion Time: 23 Months

  • Road Width: Up to 4 Lanes

  • Key Components: RCC Drain, Asphalt Concrete Road

Scope of Work:

This urban road project involved multiple layers of integrated civil works, including:

  • Construction of RCC Drainage Systems on both sides to ensure efficient stormwater management and reduce waterlogging.

  • Laying of Asphalt Concrete Pavement for a smooth, durable, and weather-resistant driving surface.

  • Road Widening and Upgrading to support up to 4 lanes, improving traffic flow and urban access.

Key Achievements:

  • Completion of a vital urban road that supports increasing traffic demand in Surkhet.

  • Improved road safety, drainage, and driving comfort for residents and commuters.

  • Contribution to the long-term development goals of Birendranagar as a growing urban hub in Karnali Province.

The successful execution of this project reflects our team’s commitment to quality, resilience, and timely delivery in urban infrastructure development.

Ratna Rajmarga, Nepalgunj Road (Jamunaha – Rajha Section)

We are proud to announce the successful completion of the Rehabilitation and Asphalt Overlay Work at Ratna Rajmarg, Jamunaha–Rajha Section, covering a total stretch of 10 kilometers. This vital section of roadway, which transitions from a 4-lane to 6-lane configuration within urban areas, plays a critical role in facilitating smooth transportation and regional connectivity in the western Terai region of Nepal.

Project Overview:

  • Project Name: Rehabilitation and Asphalt Overlay Work at Ratna Rajmarg (Jamunaha–Rajha Section)
  • Location: Banke District, Nepal
  • Road Length: 10 km
  • Lane Configuration: 4-lane to 6-lane (in city areas)
  • Project Duration: 10 Months
  • Total Asphalt Quantity: 10,151.64 m³

Scope of Work:

The project involved comprehensive roadway rehabilitation activities, including:

  • Asphalt Overlay Works for surface strengthening and smoother ride quality.
  • Semi-Grouting Repairs to address base layer deterioration and patch failures.
  • Base Compaction to ensure uniform load distribution and prevent future settlement.
  • Glass Grid Installation for crack resistance and increased pavement lifespan.

Key Achievements:

  • Timely delivery within 10 months, ensuring minimal disruption to public mobility.
  • Enhanced road durability and safety through high-quality asphalt and reinforcement techniques.
  • Significant improvement in urban traffic flow due to upgraded 6-lane segments.
This project marks another milestone in our commitment to quality infrastructure development and long-lasting transportation solutions. We thank all stakeholders, engineers, and on-ground teams who contributed to this success.